Brockman 4 Plant, Rail and Infrastructure
PROJECT CLIENT.png)
Rio Tinto
PROJECT
Brockman 4 Mine
PROJECT LOCATION
60 kilometres north west of Tom Price, Pilbara, Western Australia
PROJECT VALUE
Approximately AU $176 Million
PROJECT START DATE
July 2008
PROJECT FINISH DATE.png)
July 2009
PROJECT SUMMARY
Subsequent to the Brockman 4 Pioneering Works, this Project for all bulk earthworks (totaling 3.5 million cubic metres) for the Mine included:
- Over 50 kilometres of sealed road, built under traffic.
- Approximately 44 kilometres of railway, including a rail loop.
- A Stockpile area
- Reinforced ROM wall
- All infrastructure and plant site pads
- Permanent village earthworks
- Major mine cut off drains
- Construction of two, six metre diametre corrugated arches
- Construction of haul roads